Construction Update –  Tuesday, July 15th

Construction Update – Tuesday, July 15th

At this stage we are nearing the completion of the playground. In the past few days all of the tarmacadam has been completed, the entrance wall has been built and the installation of much of the play equipment has been finished. Work is still ongoing in relation to...
Construction Update – July 9th

Construction Update – July 9th

Construction Update: Wednesday July 9thAll of the perimeter and internal kerbing has been installed. The pillars for the entrance gate are installed. The footpath at the entrance has been replaced and the entrance is clearly defined now. The safety surfacing has been...
Construction Update – June 27th

Construction Update – June 27th

Most of the internal brick kerbing has been installed at this stage. the photos also show the rubber safety surface that has been installed around some of the play equipment. The majority of the work in the playground area will be completed in the next week after...
Construction Update – June 26th

Construction Update – June 26th

The concrete manhole at the start of the culvert is now complete. This will allow access to the culvert for maintenance and inspection. Getting this done locally has prevented this becoming an ‘extra’ in the build and has saved us accordingly. Thanks to JJ...