Play Safe & enjoy! – August 1st

GOOD NEWS  Insurance cover is now thankfully in place. We have a few minor jobs to finalise on site tomorrow. So! Pallaskenry Community Playground will be open to all from Sunday, August 3rd. Playground will be opened from 9.30 am to 9.30 pm (for summer months) Play...

Update – Sunday July 27th

We are delighted to inform you all that the playground itself is now complete. We have to finish some of the lawn areas ourselves and will be recruiting help for an evening or two soon.. All help appreciated. At this stage we are waiting for one remaining aspect of...
Construction Update –  Tuesday, July 15th

Construction Update – Tuesday, July 15th

At this stage we are nearing the completion of the playground. In the past few days all of the tarmacadam has been completed, the entrance wall has been built and the installation of much of the play equipment has been finished. Work is still ongoing in relation to...
Construction Update – July 9th

Construction Update – July 9th

Construction Update: Wednesday July 9thAll of the perimeter and internal kerbing has been installed. The pillars for the entrance gate are installed. The footpath at the entrance has been replaced and the entrance is clearly defined now. The safety surfacing has been...
Construction Update – June 27th

Construction Update – June 27th

Most of the internal brick kerbing has been installed at this stage. the photos also show the rubber safety surface that has been installed around some of the play equipment. The majority of the work in the playground area will be completed in the next week after...