Construction Update – June 26th

Construction Update – June 26th

The concrete manhole at the start of the culvert is now complete. This will allow access to the culvert for maintenance and inspection. Getting this done locally has prevented this becoming an ‘extra’ in the build and has saved us accordingly. Thanks to JJ...
June 16th – Update

June 16th – Update

This week all of the internal brick kerbs will be installed. All play areas are being prepared for the installation of the safety surface which will be installed next week. The areas between the defined sections will be surfaced with tarmacadam and will form the...
Construction Update – June 11th

Construction Update – June 11th

Construction Update – June 11thNearly all perimiter kerbing has been installed at this stage. All playground equipment is in place. The Senior play unit has been erected with its 9 foot slide, climbing wall and monkey bars.. RSS ltd as a GoPLay partner are our...